August 2002
Ran:
San Diego Daily Transcript Soaring Dimensions - Central
San Diego
Thursday, August 29, 2002
Other
construction is also taking place on the USD campus in Linda
Vista. Work began in July on a six-level, 783-space parking
structure adjacent to an existing parking lot on the west
end of campus. The $11 million structure is expected to be
complete in the spring of 2003. The architect is Innovative
Design Group in association with Mosher Drew
Watson Ferguson. The contractor is Douglas
E. Barnhart, Inc.
To help
minimize concerns about the project's impacts from USD's neighbors,
the structure will be built into a hillside, giving it a smaller
profile. Three stories will be constructed underground to
minimize height concerns and the structure's footprint has
been modified to allow the university to maintain 346 existing
surface parking spaces.
Back
|